| Case Study - 30 St Mary Axe |
This forty storey steel framed composite structure in
the heart of London's financial district, has a
surprisingly small footprint and access for the delivery
of construction materials was available only from a
narrow street. Each floor is circular and comprises an
outer ring with equally spaced radial beams plus a
central service core constructed with irregularly
spaced beams, all supporting steel decking based
composite floor slabs. The size of the core is constant,
but the outer floors vary in diameter at each level.

|
 |